The Multi-Purpose Building Project Team wishes to inform the community that work to install the sanitary sewer line at the Kahnawà:ke Cultural Arts Center Building is scheduled for the week of August 19 to 22, 2024.

QMD will be performing the civil works on the Mohawk Trail water and sewer line at the Kahnawake Survival School (KSS) entrance. Specifically, the sanitary pressure pipe, aqueduct, and culvert for the main entrance to the new Cultural Arts Center will be completed during this time, weather permitting.

The works will require that the KSS entrance be completely closed and fenced off for safety reasons. During this time, all traffic usually using this entrance should alternatively use the old KSS entrance.

This work has been scheduled for this week before the majority of staff and students return to KSS for the new school year. Please ensure that whoever requires this information has it with plenty of advance notice. We apologize in advance for any inconvenience. 

The Multi-Purpose Building Project Team reminds the public that these works are subject to change due to weather conditions, operational constraints, or work progression.